Outcome 8

2005 Strategic Planning Outcome 8 Timeline

Completion Dates
Actions
Responsibility
February 24, 2005 Determination of method for needs assessment in Jasper County Committee; Desila Rosetti
February 24, 2005 Discussion of Definition of “Cooperative and Collaborative Activities” Committee
February 24, 2005 Discussion of ways that IU Northwest can become involved in “Parents as Teachers” project and other areas of need in Starke County Committee; Desila Rosetti, Jeff Lorber
March 2, 2005 Vet initial definition of “Cooperative and Collaborative Activities” through SPC via e-mail and to SPC chairs at Chair’s meeting Jon Becker
March 24, 2005 Formalize definition of “Cooperative and Collaborative Activities” Committee; SPC
March 24, 2005 Submit and discuss Program Activity Proposals Committee
April 1, 2005(This date is flexible, based on the needs of the other outcomes) Campus e-mail to solicit information from all campus constituencies regarding activities in Lake, LaPorte, and Porter Counties Jon Becker
April 30, 2005 
(Assuming LLN Building is completed on time)
Reassessment of need for (and interest in) distance-ed courses, once Lifelong Learning Network (LLN) facilities have been completed Committee; Bob Lovely
June 15, 2005 Proposals made to appropriate contact people in Starke County Committee; Desila Rosetti, Jeff Lorber
June 30, 2005 Formalize process for Sustaining Outreach in Newton County Committee
July 31, 2005 Meet with representatives from Starke County Committee
August 15, 2005 Collect and collate data as it comes in, following up via e-mail to clarify activities as needed. Committee
September 16, 2005 Follow-up campus e-mail to determine any new activities that may have started during the new academic year Jon Becker
September 30, 2005 Collect and collate any additional data as it comes in, following up with e-mails to clarify activities as needed Committee
October 15, 2005 Initiate Activity in Starke County Committee
September 30, 2005 Conduct Needs Assessment in Jasper County Desila Rosetti: Office of Management Development
October 31, 2005 Needs Assessment Report Due Jon Becker
November 30, 2005 “Cooperative/Collaborative Activities” Report Due Jon Becker
December 15, 2005 Newton County Outreach Report Due Jon Becker
December 31, 2005 Starke County Activity Report Due Jon Becker

2005 Strategic Planning Outcome 8 Deliverables