2012 Web Redesign Project
Timeline with Milestones
- Template Development - December 2011 through June 2012
- Template Review with Project Sponsor - May 2012
- Preliminary meetings with key stakeholders - May 2012
- Milestone: Assemble Project resources - May 14, 2012
- Milestone: Assemble Project Team and Official Project Kickoff - May 16, 2012
- Milestone: Template Approval - May 22, 2012
- Define and test migration process -
- Inventory sites and assign to migration team June 1, 2012
- Campus wide Info sessions - June 5 & 6, 2012
- Training - August 2012
- Milestone: Academic Marketing and Technology sites to be completed October 10, 2012
- External Relations
- Marketing News
- Other Marketing sites
- Alumni Affairs
- Academic site - top levels and departments/programs
- COAS
- BUSE
- CHHS
- Library
- Education
- Training - December 2012
- Milestone: Administrative sites to be completed January 15, 2013
- Sites not part of the Phose II and Phase III - miscellaneous other sites
- Additional Training
- Development of Analytic reports
- Milestone: Project Completion: - May 15, 2013