  1. Template Development - December 2011 through June 2012
  2. Template Review with Project Sponsor - May 2012
  3. Preliminary meetings with key stakeholders - May 2012
  4. Milestone: Assemble Project resources - May 14, 2012
  5. Milestone: Assemble Project Team and Official Project Kickoff - May 16, 2012
  6. Milestone: Template Approval - May 22, 2012
  7. Define and test migration process -
  8. Inventory sites and assign to migration team June 1, 2012
  9. Campus wide Info sessions - June 5 & 6, 2012
  10. Training - August 2012
  11. Milestone: Academic Marketing and Technology sites to be completed October 10, 2012
    • External Relations
      • Marketing News
      • Other Marketing sites
      • Alumni Affairs
    • Academic site - top levels and departments/programs
      • COAS
      • BUSE
      • CHHS
      • Library
      • Education
  12. Training - December 2012
  13. Milestone: Administrative sites to be completed January 15, 2013
  14. Sites not part of the Phose II and Phase III - miscellaneous other sites
  15. Additional Training
  16. Development of Analytic reports
  17. Milestone: Project Completion: - May 15, 2013